Simulating your house before choosing the work
When the question is about something that varies over time — overheating, the thermal mass of the walls, the effect of airing at night — the house is modelled and then simulated hour by hour over a whole year. Several scenarios of works or of use are then compared, to find out what each one really changes, in winter and in summer.
- Indicative price
- from €1,200Without a simulation of your house; with one, usually between €2,000 and €3,000. For a €50,000 project, that’s 4 to 6%: often less than the cost of one poorly chosen stage of works.Prices include all taxes. The exact price is in the quote, sent after the free first conversation.The simulation is part of “Prepare a renovation” →
What it can show, depending on scope
- how temperatures change over days and seasons
- overheating indicators
- heating demand
- a comparison of scenarios of works or of use
- how sensitive the results are to the assumptions
What depends on the data and the job
A room-by-room study, a model calibrated against measurements or future-climate scenarios are possible in some cases: it depends on the data available, on how the house is divided into zones and on the agreed scope.
The calculation is run with EnergyPlus, a reference simulation engine developed for the US Department of Energy. The software computes; the value of the study lies in the assumptions chosen, how they are checked, and how the results are read.
Steady-state calculation or dynamic simulation?
These are two methods, chosen according to the question to be settled.
- A simplified, steady-state calculation answers some winter questions or targeted comparisons: an order of magnitude for heat losses, for example.
- A dynamic simulation is useful as soon as temperatures need to be followed over time: overheating, thermal mass, variable occupancy, cooling strategies.
Even in a study focused on winter, the risk of summer overheating and the effects on ventilation are examined qualitatively.
What the figures mean
Calculated heating demand is the energy needed to hold the set temperatures. It is neither your consumption nor your bills, which also depend on the heating system, the fuel used and your habits. It is there to compare scenarios with one another.
When the cost of works is looked at, it remains indicative: builders’ quotes are what fix it.
A real example, from survey to decision
A real exampleSimulation results
A stone house in southern Haute-Vienne
What does the project change, and what still depends on the people who live there?
What we observe
A two-storey stone house, walls 54 cm thick, 144 m² of living space. On the ground floor the walls are bare; upstairs, the insulation is old; the wooden windows have old double glazing.
What we assume
A typical weather year for Limoges-Bellegarde. The same occupancy and the same heating set-points (20 °C by day, 18 °C at night) in both scenarios: the differences therefore come from the works, not from habits.
What we compare
The house before works and the project, stage by stage: ground floor and floor over the cellar, then upstairs, then the glazing. Then the same calculations with different habits: shutters, airing at night, heating set-point.
1 · What the project brings
Winter is a different season
Heating demand
16,673Before works, Project: 5,035
kWh/year · divided by 3.3
Winter: hours too cool
26Before works, Project: 1
% of hours at home · same set-point
Felt temperature in winter
18.6Before works, Project: 19.9
°C, October to April · the walls no longer chill the room
Before worksProject
2 · How far to go?
The first stage brings most of the gain
Remaining heating demand, in kWh/year, as each stage is added in the order of the works. Each stage is simulated with the previous ones already done.
Re-glazing while keeping the wooden windows brings almost nothing for heating; it also lets in slightly less sun, a small plus in summer. This stage is therefore decided on other grounds (state of the glazing, comfort near the windows, cost): the owners have not kept it for now and will do it later, as it isn’t a priority. Stopping after any stage keeps the gain made so far.
Variant studied
Lining the ground floor with wood fibre, like upstairs, would do better on paper: 4,100 kWh/year instead of 5,035. The owners preferred a lime-hemp render: it takes less room space and stays compatible with the old masonry. Upstairs is almost all roof slopes and ceilings: wood fibre was extended to the few walls there so as to have a single system. The calculation informs the choice; the people who live there make it.
3 · What depends on you
Insulated, the house holds its heat better — summer heat too
Summer: share of hours too hot with the project, depending on what the occupants do. The line marks the same house before works, with the same habits.
ProjectBefore works, same habits
Without shutters closed in time, the insulated house gets hotter in summer than before the works.
In winter, the same trade-off
With the project, depending on the daytime set-point.
19 °C
4,213 kWh/year
17.6% of hours too cool
20 °Cbaseline
5,035 kWh/year
1.1% of hours too cool
21 °C
5,927 kWh/year
0.0% of hours too cool
One degree lower saves about 800 kWh a year, but nearly one hour in six becomes too cool.
Each habit was simulated for both states of the house, to see whether the project’s advantage holds when habits change. This needs discussing with the occupants before the works: can they close the shutters during the day? Open up at night, despite noise or being away?
4 · Put through a heatwave
It doesn’t get as hot, but stays hot for longer
Recent summers have been a reminder: a renovation must also be judged on how it copes with heat. This project was therefore put through an extreme episode, to find out what insulation can do and what it cannot.
A separate simulation, designed as a stress test: fourteen consecutive days, up to 42 °C in the afternoon and 27 °C at night. A severe episode, not a forecast.
Peak felt temperature
36.2Before works, Project: 33.5
°C · −2.6 °C
Warmest night
30.7Before works, Project: 29.9
°C felt · 34.3 °C without airing at night
Hours above 28 °C
231Before works, Project: 295
hours · 64 h more
And air conditioning?
To keep the air in the renovated house below 26 °C at all times, about 60 kWh of heat would need removing over a typical year, but 420 kWh, with a peak of 2.7 kW, during those two weeks. A modest order of magnitude: enough to consider active cooling when the time comes, at least for one “refuge” room.
The whole study, in short
What the study really says
- The works deal with winter, and the first stage (ground floor and floor over the cellar) does most of it.
- Summer no longer depends on the walls alone: depending on whether the shutters are closed in time and the house can be aired at night, the same house goes from comfortable to hotter than before the works.
- In a long heatwave, insulation alone isn’t enough: habits, a refuge room or active cooling need planning now, even if they aren’t installed straight away.
- The calculation informs the choice; the people who live there make it.
What the owners didn’t do, and why
What was left out matters as much as the works: each choice was weighed, with figures.
No heat-recovery ventilation
About 1,500 kWh of heating saved a year, for €4,000 more, filters to replace and more electricity. A good single-flow system is enough here.
No air conditioning throughout
A reversible heat pump for one bedroom and a “refuge” room: enough to get through a heatwave without equipping every room.
No new glazing for now
341 kWh a year, almost nothing for heating. The stage is postponed: the owners will do it later, as it isn’t a priority.
No wood fibre on the ground floor
Better on paper (4,100 kWh/year instead of 5,035), but the lime-hemp render takes up less room and stays compatible with the old masonry.
The adviser’s reading and the decision
The finding
Insulation brings undeniable comfort: heating demand falls from about 16,700 to 5,000 kWh a year. Heatwaves remain the weak point: during the simulated episode, no night drops below 26 °C in the bedrooms. Insulating further would make little difference; after habits, it is equipment (air conditioning, geocooling, adiabatic cooling, etc.) that will take over.
Needs first
The study establishes heating and cooling needs; equipment is then chosen from those needs. Only ventilation acts directly on them. A heat-recovery ventilation system would recover about 90% of its losses, close to 1,500 kWh a year, for an extra cost of around €4,000, not counting filters or higher electricity use.
The choices made
A good single-flow mechanical ventilation system, simpler to maintain, as the owners wish. A wood stove for the main heating, with wood available on the property: peak demand stays modest (5 kW over a typical year, 8 kW in a cold snap). Upstairs, a reversible air-to-air heat pump to cool a bedroom and a “refuge” room, and to top up the heat in these rooms far from the stove. The glazing, of little use for heating, is postponed.
What this study doesn’t say
- This is heating demand, not a bill: actual consumption also depends on the heating system, the fuel used and real habits.
- Moisture in the old walls is not modelled by this calculation.
- Comfort rests on assumptions about clothing and activity, which are set rather than measured.
- The weather is a typical year: it describes the recent climate, not that of the decades ahead.
EnergyPlus dynamic thermal simulations: before works, the project stage by stage, use assumptions and a heatwave episode. Results specific to this house.
Planning building work? Let’s see whether a simulation is worth it.
Describe your house and what you have in mind. The first conversation is free: it’s for seeing whether the question needs a simulation, or whether a simpler calculation will do.
Talk about my house